The Town Council continues to enhance our estates with various Town Improvement Projects, where new amenities and facilities are progressively added and/or upgraded to meet the needs and evolving aspirations of our residents.
Here’s the list of ongoing/upcoming improvement projects in the estate:
S/No. | Type of Works | Location | Commencement Date | Estimated Completion Date | Remarks |
1 | Upgrading of Existing High Covered Linkway | At Block 1 Dover Road | 4th Quarter 2019 | 1st Quarter 2022 | Completed 😀 |
2 | Construction of Covered Linkway over Existing Ramp | Between Block 64 and 67 Telok Blangah Drive | 4th Quarter 2019 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
3 | Construction of Children’s Playground | Beside Block 268C Boon Lay Drive | 3rd Quarter 2021 | 2nd Quarter 2022 | Completed in Mar 2022 😀 |
4 | Upgrading of Existing Fitness Corner | At Block 209 Boon Lay Place | 3rd Quarter 2021 | 2nd Quarter 2022 | Completed in Mar 2022 😀 |
5 | Upgrading of Children’s Playground | Near Block 659D Jurong West Street 65 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed 😀 |
6 | Upgrading of Children’s Playground | Near Block 652C Jurong West Street 61 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
7 | Upgrading of Children’s Playground | Near Block 650A Jurong West Street 61 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed in Mar 2022 😀 |
8 | Upgrading of Children’s Playground | Near Block 649B Jurong West Street 61 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed 😀 |
9 | Upgrading of Children’s Playground | Near Block 610 Jurong West Street 65 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed in Dec 2021 😀 |
10 | Upgrading of Children’s Playground | Near Block 605 Jurong West Street 62 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
11 | Upgrading of Children’s Playground | Near Block 602 Jurong West Street 62 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
12 | Upgrading of Children’s Playground | Near Block 663B Jurong West Street 65 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed in Mar 2022 😀 |
13 | Upgrading of Children’s Playground | Near Block 664B Jurong West Street 65 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
14 | Construction of Resident’s Corner | Block 639 Jurong West Street 61 | 1st Quarter 2022 | 4th Quarter 2022 | In Progress |
15 | Upgrading of Existing Fitness Corner | Block 669B Jurong West Street 64 | 2nd Quarter 2021 | 1st Quarter 2022 | Completed in Feb 2022 😀 |
16 | Upgrading of Existing Fitness Corner | Block 629 Jurong West Street 65 | 2nd Quarter 2021 | 1st Quarter 2022 | Completed in Feb 2022 😀 |
17 | Construction of Community Garden | Roof deck of MSCP Block 183 Boon Lay Avenue | 2nd Quarter 2021 | 4th Quarter 2021 | Completed in Nov 2021 😀 |
18 | Upgrading of Children’s Playground | Near Block 275A Jurong West St. 25 | 2nd Quarter 2021 | 3rd Quarter 2021 | Completed in Jul 2021 😀 |
19 | Upgrading of Children’s Playground | Near Block 272C Jurong West St. 245 | 2nd Quarter 2021 | 3rd Quarter 2021 | Completed in Jul 2021 😀 |
20 | Upgrading of Existing Residents’ Corner | At Block 52 Teban Gardens Road | 4th Quarter 2021 | 3rd Quarter 2022 | In Progress |
21 | Upgrading of Existing Street Soccer Court to a Futsal Court | At Block 410 Pandan Gardens | 2nd Quarter 2021 | 3rd Quarter 2022 | In Progress |
22 | Upgrading of Existing Street Soccer Court to a Futsal Court | Behind Block 41 Teban Gardens Road | 2nd Quarter 2021 | 3rd Quarter 2022 | In Progress |
23 | Construction of Covered Walkway at Shop Front | Block 49 and 54 Teban Gardens Road | 2nd Quarter 2021 | 2nd Quarter 2022 | In Progress |
24 | Construction of Footpath (with lightings) |
Near Block 683A and 683B Jurong West Central 1 | 3rd Quarter 2021 | 3rd Quarter 2022 | In Progress |
25 | Construction of Footpath (with lightings) |
Along service road near Block 678C & 677C Jurong West Street 64 (Existing badminton court Block 677 & Block 680C Jurong West Street 64) | 3rd Quarter 2021 | 3rd Quarter 2022 | In Progress |
26 | Construction of Landmark Structure | In front of Block 986C Jurong West Street 93 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed 😀 |
27 | Construction of Landmark Structure | In front of Block 641 Jurong West Street 61 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed 😀 |
28 | Construction of Landmark Structure | In front of Block 649A Jurong West Street 61 | 3rd Quarter 2021 | 1st Quarter 2022 | Completed 😀 |
29 | Construction of Landmark Structure | In front of Block 661B Jurong West Street 64 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
30 | Construction of Landmark Structure | In front of Block 694 Jurong West Central 1 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
31 | Construction of Landmark Structure | In front of Block 698C Jurong West Central 3 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
32 | Upgrading of Elderly Fitness Corner | Near Block 692 Jurong West Central 1 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
33 | Upgrading of Elderly Fitness Corner | Near Block 663E Jurong West Street 64 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
34 | Upgrading of Elderly Fitness Corner | Near Block 660C Jurong West Street 64 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
35 | Upgrading of Elderly Fitness Corner | Near Block 658C Jurong West Street 61 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
36 | Upgrading of Adult Fitness Corner | Near Block 656A Jurong West Street 61 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
37 | Upgrading of Adult Fitness Corner | Near Block 654C Jurong West Street 61 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
38 | Upgrading of Children’s Playground | Near Block 660A Jurong West Street 64 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
39 | Upgrading of Children’s Playground | Near Block 656D Jurong West Street 61 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
40 | Installation of Overhead Fan at Community Plaza | In front of Block 688 Jurong West Central 1 | 3rd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
41 | Upgrading of Children’s Playground | Between Block 941 and 944 Jurong West Street 91 | 3rd Quarter 2021 | 2nd Quarter 2022 | Completed in Feb 2022 😀 |
42 | Upgrading of Senior Citizen Fitness Corner | Near Block 953 Jurong West Street 91 | 3rd Quarter 2021 | 2nd Quarter 2022 | In Progress |
43 | Upgrading of Open Space | Near gable end of Block 52 to 53, 63 to 64 and 65 Telok Blangah Drive/Heights | 1st Quarter 2022 | 3rd Quarter 2022 | In Progress |
44 | Upgrading of Existing Senior Citizen’s Corner to Resident’s Corner | At Block 603 Jurong West Street 62 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
45 | Construction of Low Covered Linkway | From Block 698B Jurong West Central 3 to RN Centre | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
46 | Construction of Low Covered Linkway | From Block 698C Jurong West Central 3 to Existing LTA Linkway | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
47 | Construction of Low Covered Linkway | From new school gate of Jurong West Primary School to MSCP at Block 601A Jurong West Street 62 | 3rd Quarter 2021 | 2nd Quarter 2022 | Completed 😀 |
48 | Construction of Covered Linkway cum Drop-off Point | Near Block 662A Jurong West Street 64 | 2nd Quarter 2022 | 2nd Quarter 2023 | NIL |
49 | Construction of Covered Linkway cum Drop off-Point | Between Block 663A and 663B Jurong West Street 65 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
50 | Proposed Barrier-Free Access (BFA) Ramp | Near Block 692A Jurong West Central 1 | 4th Quarter 2022 | 4th Quarter 2023 | NIL |
51 | Proposed High and Low Covered Linkway | From Blk 32 to 64 Teban Gardens | 1st Quarter 2021 | 2nd Quarter 2022 | Completed 😀 |
52 | Construction of High / Low Covered Linkway | From Block 716 to 722 Clementi West Street 2 | 2nd Quarter 2021 | 3rd Quarter 2022 | Completed😀 |
53 | Construction of High / Low Covered Linkway | Block 601 to 609 and Bus stop at Clementi West Street 1 | 2nd Quarter 2021 | 3rd Quarter 2022 | Completed😀 |
54 | Upgrading of existing Senior Citizen Comer | Block 511 West Coast Drive | 2nd Quarter 2022 | 3rd Quarter 2022 | Will complete 1st Quarter 2023 |
55 | Construction of BFA Ramp | Block 52 Telok Blangah Drive | 2nd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
56 | Construction of BFA Ramp | Block 111A Depot Rd | 2nd Quarter 2021 | 4th Quarter 2021 | Completed in Dec 2021 😀 |
57 | Construction of a new Standalone Handicap Toilet | Near Block 221A Boon Lay Place | 3rd Quarter 2021 | 3rd Quarter 2022 | In Progress |
58 | Construction of Drop Off Porch | Near Block 197B Boon Lay Drive | 1st Quarter 2022 | 3rd Quarter 2022 | In Progress |
59 | Construction of Pavilion | Near Block 200 Boon Lay Drive | 1st Quarter 2022 | 3rd Quarter 2022 | In Progress |
60 | Upgrading of Existing Residents’ Corner | At Block 218A Boon Lay Avenue | 1st Quarter 2022 | 3rd Quarter 2022 | In Progress |
61 | Construction of Covered Linkway with Drop-off Point | Block 673A Jurong West St 65 | 1st Quarter 2022 | 3rd Quarter 2022 | In Progress |
62 | Construction of Covered Linkway with a Wash Area near Existing Park Shelter | Near existing Park Shelter near MSCP Block 673 Jurong West St 65 | 3rd Quarter 2019 | 4th Quarter 2020 | Completed 😀 |
63 | Construction of Covered Linkway | Linking Block 632 to bus-stop near Block 673 Jurong West Street 61 | 2nd Quarter 2021 | 2nd Quarter 2022 | In Progress |
64 | Construction of Bicycle Shed with Double Tier Bicycle Racks and Covered Linkway | Near Block 625 Jurong West St. 61 | 1st Quarter 2020 | 1st Quarter 2021 | Completed 😀 |
65 | Construct Concrete Footpath | Along internal driveway near Block 677 and 680C Jurong West Street 64/ Central 1 | 3rd Quarter 2021 | 3rd Quarter 2022 | In Progress |
66 | Construction of Footpath | Near MSCP Block 216 Boon Lay Drive | 3rd Quarter 2021 | 4th Quarter 2021 | In Progress |
67 | Replacement of existing taps to sensor types | Block 221B Boon Lay Place Food Centre | 3rd Quarter 2021 | 4th Quarter 2021 | In Progress |
68 | Construction of High/Low Covered Linkway | Between Blocks 865 & 859A | 3rd Quarter 2022 | 2nd Quarter 2023 | Nil |
69 | Construction of Covered Linkway | From Block 2A Dover Rd to LTA built Covered Linkway at Dover Rise | 4th Quarter 2019 | 4th Quarter 2021 | Completed 😀 |
70 | Upgrading of Playground to Elderly Fitness Corner | Blocks 509 and 510 West Coast Drive | 3rd Quarter 2021 | 4th Quarter 2021 | Completed 😀 |
71 | Construction of Bicycle Shed | In front of Block 658D and Link Building at Block 658 Jurong West St 65 | – | – | Completed in Mar 2021 😀 |
72 | Construction of Bicycle Shed | In front of Block 659 Jurong West St 65 (MSCP) | – | – | Completed in Mar 2021 😀 |
73 | Construction of Bicycle Shed | Near Block 666A Jurong West St 65 | – | – | Completed in Mar 2021 😀 |
74 | Construction of Bicycle Shed | In between Block 990 (MSCP) & Block 988C Jurong West St 93 | – | – | Completed in Mar 2021 😀 |
75 | Construction of Bicycle Shed | In front of Block 656C & Block 656D Jurong West St 61 | – | – | Completed in Mar 2021 😀 |
76 | Construction of Bicycle Shed | Near Block 661B and Block 661C Jurong West St 64 | – | – | Completed in Mar 2021 😀 |