Cyclical Maintenance

 

 S/N

 Type of Works

 Blocks

 Commencement Date

 Estimated Completion Date

1.

Cyclical Replacement of Lifts

 Block 257 to 266 Boon Lay Drive

 2nd Quarter 2018

 2nd Quarter 2020

2.

Repairs and Redecoration

Block 257 to 267 Boon Lay Drive

2nd Quarter 2018

1st Quarter 2020

3.

Block 663A-D, 664A-D, 665A-B, 666A-B
Jurong West Street 64/65

1st Quarter 2019

2nd Quarter 2020

4.

Block 617 to 637 Jurong West Street 61/65

3rd Quarter 2019

4th Quarter 2020

5.

Block 679A-C, 680A-C, 681A-C, 682A-C, 683A-C, 684A-C, 685A-C, 686A-C Jurong
West Central 1/Street 64

3rd Quarter 2019

4th Quarter 2020

6.

Block 20 to 23, 20A, 21A Teban Gardens Road

4th Quarter 2019

4th Quarter 2020

7.

Replacement of fibre glass reinforced polyester (FRP/GRP) sectional water tanks

Block 185, 186 & 206 Boon Lay Ave/ Drive

4th Quarter 2019

3rd Quarter 2020

8.

Lift Enhancement works

Block 60 Telok Blangah Heights (Lift C)

 1st Quarter 2020

1st Quarter 2020